Clear what the approved plan and next trade need—not an undefined extra area.

The order of operations on a building lot matters more than the price of any single step. Survey first, because clearing an area the plan later moves is money spent twice and screening lost for nothing. Then approvals, then utility location, then erosion controls installed, and only then the clearing — and only the approved plan area, staked on the ground. Clear the investigation access before the full envelope, so the geotechnical, septic and drainage work can happen while the position of the house is still adjustable. Total the earth disturbance across the whole plan rather than per phase, because Vermont's Construction General Permit triggers at one acre including anything that is part of a larger common plan of development. Low Risk coverage requires temporary or final stabilisation within 14 days of initial disturbance, and that clock starts when the first machine moves, not when the builder arrives.

Sequence, and what goes wrong when it slips
StepBeforeIf it slips
Boundary surveyEverythingCleared area in the wrong place, or a trespass
ApprovalsAny disturbanceStop-work and retroactive permitting
Utility locationAny machine workA struck service
Erosion controlsFirst disturbanceSediment leaving the site
Investigation accessFull envelope clearingThe house moves after the screening is gone
Envelope clearingExcavationClearing twice
StabilisationWithin 14 days of disturbancePermit non-compliance

Sequence the project around verified information

Survey and approvals come before broad clearing. Open only the access, test area, trail, fence corridor, or building envelope the next step requires.

Mark retained features and write the material outcome, finish tolerance, exclusions, stop-work conditions, and change-order process.

Collect evidence from the property

Send one marked aerial, a map pin, a photo from the equipment approach, wide views from both directions, a close view of typical density, the largest stem beside a tape or familiar object, slope and wet-ground views, gates, turns, overhead clearance, and anything the machine must avoid.

The sequence, in order

  1. Get the approved site plan with the limit of disturbance drawn on it.
  2. Stake the limit of disturbance on the ground.
  3. Total disturbance across the whole plan for the stormwater threshold.
  4. Install erosion controls before the first machine.
  5. Clear investigation access only, then wait for results.
  6. Clear the envelope once the position is fixed.
  7. Stabilise on schedule regardless of when the builder starts.

The order is the useful part. Every one of the failures in the next section is a step from this list taken out of sequence or skipped entirely.

What goes wrong

  • Clearing before the septic and drainage investigation.
  • Counting acreage per phase.
  • Removing screening that the finished house needed.